The Nodin Kitagan Partnerships have undertaken rigorous design and study work to prepare a complete Renewable Energy Approval (“REA”) application. Draft REA documents, including Natural and Cultural Heritage Assessment documents, are available for review in the Regulatory Approvals and Documentation Page, and hard copies are available at the Sault North Planning Board Office (669 Wellington Street East, Sault Ste. Marie).

The Final Public Meeting is scheduled for December 13, 2012, from 5:00 until 8:00 pm at the Aweres Public School. Subsequent to that meeting, we will work to update and finalize its REA application documents based on feedback from that final meeting, and to submit an REA application to the Ministry of Environment early in 2013. Should the Project be successful in receiving environmental approvals, construction could start in the summer of 2013. The Project has issued the first newsletter which is available here for further project information.